Costs force Grand Isle to shrink library plans

GRAND ISLE – Town officials in Grand Isle have downsized their plans for a new library building after cost estimates for the planned library and community building came in well above the town’s original budget.

According to comments from local officials during recent selectboard and planning commission meetings, Grand Isle officials are now focusing on developing a smaller, dedicated library building without an adjoining community room after construction estimates placed the development of a combined library and community space at more than $3.7 million.

Those estimates, according to members of the town’s planning commission, came from a detailed estimate provided by Connor Contracting, a general contracting firm with offices in Berlin and St. Albans serving as the construction manager for the Grand Isle library project.

According to town officials, Grand Isle initially had around $2.3 million budgeted for the library project between an almost $1.7 million federal grant awarded through the Vermont Dept. of Libraries and another roughly $600,000 in American Rescue Plan Act funds earmarked by Grand Isle officials for developing a new library building.

Since receiving federal funding through the state, town officials have discussed building a new library and community building with a roughly $2 million budget, as some of the funding earmarked for the new Grand Isle library had already been spent on architectural and engineering fees. Local officials previously said they had anticipated some “value engineering” would be needed to manage construction costs.

The news that Grand Isle would have to dramatically shrink its long anticipated library development, however, was met with visible frustration by local officials.

“It’s draining,” Jeff Parizo, the Grand Isle selectboard’s chair and one of the selectboard’s members most involved in the library project, said during a recent selectboard meeting.

For years now, officials in Grand Isle have looked to replace the Grand Isle Free Library with a new library building raised nearby on Hyde Road. Built roughly a century ago, the 900 square foot building currently housing the Grand Isle library has long been short on space, with bookshelves leaving little room for the community activities, meeting spaces and technology services considered the norm for modern libraries.

The Town of Grand Isle’s recently updated municipal plan explicitly cites the need for a new library building as a priority for local planners, calling for the development of a library “designed to meet the current and future needs of the town” and envisioning a new library built near Grand Isle’s current town offices as “the cornerstone of the new municipal town center.”

According to the town’s plans for a new library, the historic Grand Isle Free Library building would be preserved and repurposed, though officials have yet to formally discuss future uses for the building.

As a result of unexpectedly high construction costs, Grand Isle officials working on the library project have agreed to wholly remove a planned community space meant to extend from the library and have relocated some of the infrastructure and amenities needed for a public building, including restrooms, from the community space into the new library itself, reducing the amount of space within the building for dedicated library services.

Officials also said they were limited by some engineering demands for the project and by a deadline for the Vermont Dept. of Libraries grant that required a new library be open by next December. Because of the quick turnaround for revised plans needed for construction to begin in time for a 2026 opening, officials said they would need to preserve some of the original library project’s mechanical systems.

Given the higher construction costs and tight deadline for construction, town planners said they had little choice but to remove the community room from their library plans after conversations with architects and the construction manager failed to find other ways to meaningfully reduce the costs for the new library building.

“At the end of the day, we had to get the building to 4,000 square feet,” Jennifer Morway, a member of Grand Isle’s selectboard and planning commission, said during an August planning commission meeting. “There wasn’t a choice but to cut the community room.”

As of the town selectboard’s most recent regular meeting, Grand Isle officials said they were still working with plans for a roughly 4,000 square foot library building and were now communicating with the town’s highway department about managing some of the project’s sitework, but added that construction costs might force officials to further shrink their planned library’s footprint over the coming weeks.

“If we have to cut more money off of this, the building is going to have to shrink,” Parizo, the Grand Isle selectboard’s chair, said when the selectboard met last week. “That’s the only way we’re going to save money at this point – by losing square footage.”

The library project has received most of its required permitting, according to officials. The Town of Grand Isle’s development review board recently approved the project following a brief August hearing, and town officials said last week that the project had passed its review under Act 250, Vermont’s preeminent land use law typically applied to larger developments and projects in more sensitive areas.

It was immediately unclear how changes to the library project would affect its eventual construction timeline, but town officials said they planned to continue pursuing the library’s development.

“The pressure’s on,” Parizo said. “The foot’s still on the pedal, and we’re still pushing through.”

Leave a Reply