North Hero opts for smaller $3.5 million fire station, highway garage bond

NORTH HERO – The Town of North Hero has agreed to a $3.5 million bond to help fund the development of a new fire station and public works garage after construction bids placed the expected costs for the new buildings well beneath an initially assumed $5.2 million price tag.
The town’s selectboard voted earlier this month to seek a smaller bond than the $4.5 million amount approved by North Hero voters in September after officials agreed to contract with DEW Construction Corporation, a New England-based firm with a Williston office promising to build the new fire station and town garage for less than $3.3 million.
According to information presented to the town’s selectboard, the estimated costs for what officials have called “the North Station building replacement” were now closer to $4 million between expected costs for construction, preconstruction work like permitting and engineering, and furnishing and equipment for North Hero’s new fire station and public works facility once both garages were built.
The revised bond amount incorporates roughly $300,000 in contingency funding and would see the remaining building costs covered by approximately $800,000 in reserve funds previously allocated by North Hero toward rebuilding its North Station. The town has already spent another $149,000 from its reserves to cover certain preconstruction costs, according to North Hero officials.
When speaking with the selectboard in early December, Matthew Reed, an architect from AES Northeast assigned to the North Station’s replacement, said DEW Construction Corporation was able to keep prices comparatively low by handling more work in-house rather than through subcontracting. The company’s construction bid was the least expensive of the six bids reviewed by North Hero officials.
“They were able to appease and explain all the areas of concern for us,” Reed told the selectboard when explaining his firm’s endorsement for contracting with the DEW Construction Corporation.
Replacing the garage shared by North Hero’s highway department and its volunteer fire department has been a longstanding goal for town officials. For years, North Hero officials have highlighted damage to the building and the little space available in its garage to safely accommodate the larger vehicles more typical of more modern fire departments and public works programs.
Officials paused their work to replace the North Station for a time as the community weathered the first years of the COVID-19 pandemic, but planning gradually resumed and, by this summer, a volunteer North Station building replacement committee floated a $4.5 million bond to North Hero voters to help fund what officials initially expected to be a $5.2 million development.
According to the plans pitched to North Hero voters, the single Route 2 garage used by the North Hero Volunteer Fire Department and the town’s highway department would be replaced by two separate garages designed to accommodate the larger vehicles used by both departments. The two buildings would include updated amenities, including office space and, for the fire department, showers.
When agreeing to a $3.5 million bond earlier this month, officials also settled on a 30-year repayment plan that would see annual bond payments of around $116,000 once construction started.
While the longer repayment period would ultimately see North Hero pay $900,000 more in interest than the town would have paid under a shorter 20-year repayment plan also weighed by North Hero officials, selectboard members said news about an anticipated increase in education taxes this year pushed them into favoring smaller annual bond payments.
North Hero officials were primarily referencing a report from the Vermont Dept. of Taxes and the state legislature’s joint fiscal office suggesting that, without action from Vermont’s legislature, education taxes would increase by an estimated 12% across Vermont next year due to the rising costs of maintaining the state’s public education system amid a continued decline in student enrollment.
Similar issues with managing climbing education costs previously forced the Champlain Islands Unified Union School District to stop offering classroom programming at its elementary school in North Hero.
“It feels like I’m in between a rock and a hard place here trying to get an important project done that I think is meaningful for our town while, at the same time, spending our future dollars to subsidize the state of Vermont,” selectperson Harry Parker said. “That’s not a position I like being in.”
“If they’re going to keep double digit taxes this year, and year after year, it’s going to be very hard,” the selectboard’s vice chair Joe Latimer agreed. “Especially knowing the demographics of this community.”
Construction for the new municipal garages is expected to begin this coming spring. According to town officials, North Hero’s contract with the DEW Construction Corporation would see the new highway department garage and fire station largely finished and ready for the two departments’ return before the following winter.
Each of the North Hero selectboard’s votes approving a contract with the DEW Construction Corporation and a 30-year repayment plan for the town’s $3.5 million bond were unanimous.